Import and Export Project Data

1. Export Project information to update your third-party system. 2. Import Project data from your third-party project management system.

Introduction

Export Project Data


Introduction

You can export Project data information to be used in another system, e.g. CostCon.

This allows you to take the Project Cost Codes and budgets and variations back to your Project management system to ensure that you are using the most up to date data.

Return to Top of Page


Export Project Data

To export data for a Project:

  • Go to Time sheets > Projects, or Expenses > Projects.
  • Search and select the Project you require.
  • Go to the Cost Codes tab.
  • Click the down arrow beside Export / Import.
  • Click Export to Spreadsheet.

This will create an .XLXS spreadsheet for you.

Return to Top of Page


Need more help? We’re here! We hope our article was helpful! If you need more info or want to connect, drop us an email at support@lentune.com.

Thank you. We love to hear from you!